This page is simply a story-telling photo history of the project supported by short narratives. The most recent photos display first. This page is best viewed with a large display such as a laptop, iPad, etc.
The Home Page also has updates in the Keeping You Informed link.
The remaining work after the May 25th post is wiring, connection to the electrical panel, etc.
As such, it is not expected that there will be future updates to this page.
Last update: May 27, 2024 4:00 p.m.
Saturday, May 25. 2024, 3:45 p.m.
South facing canopy, completed. All done, both canopies.
The basic panel installation is completed. Next week is the wiring, micro inverters, lighting and other steps to complete the canopy installation which is expected to be done by Friday. After that it's the wiring, conduit, connection to the electrical panel/switchgear. which is mostly work where the visual progress is a challenge to show. Since the remaining installation steps are not all that conducive to photo-story telling, it is not expected there will be future posts to this page.
Saturday, May 25. 2024, 1:30 p.m.
Good progress with the south facing canopy.
Looks like it will be done today.
Saturday, May 25, 2024, 9:35 a.m.
Wrapping up the west facing canopy.
Friday, May 24, 2024, 4:30 p.m.
Slight delay today due to lift malfunction.
Done for the day...West facing canopy almost done
Friday, May 24, 2024, 11:30 a.m.
Panel Installation. Early in the process, much more to go
Friday, May 24, 2024, 11:30 a.m.
Trenching
Thursday, May 23, 2024 4:30 p.m.
Trenching
Thursday, May 23, 2024 10:00 a.m.
Panels delivered
Day 11, Thursday, May 9, 2024 3:20 p.m.
Installation of support beams and solar panel support beams:
All done with structure.
Of interest, start to finish in 9 working days with 4-5 days actual installation and 4-5 days waiting for inspection and inspection, some overlap.
Day 9, May 7, Day 10 May 8 and Day 11 May 9, 2024
Installing support beams and solar panel beams:
Cement pour and start of support beams:
Day 8, Monday, May 6, 2024 -The last of three Inspections completed.
Day 9, Tuesday, May 7, 2024 10:45 a.m. Concrete poured.
Photos 2 & 3 look like rebar prep:
Day 2-5, Ending May 5, 2024
Soil and related inspection completed, waiting for structural inspection. Only upcoming needed steel has been delivered to save on space within the fencing. Electrical inspection signed-off about 3:30 p.m. Friday, May 5. Mechanical/rebar/radius/etc. inspection Monday:
Day 2, Tuesday, April 30, 2024-10:00 a.m. All posts are in, but concrete not poured,
pending city inspection which should be in 2-3 days:
Day 1, Monday, April 29, 2024-10:00 a.m. Boring.
The boring was completed, and some posts put in place later by end of day:
Friday, April 26, 2024 - Fencing.
Day 1 of installation: Monday April 29:
The solar permit was officially issued on April 5, 2024 after a near one-year wait but as expected from the history of similar projects and the City's timeline.
Contractor scheduling was immediately done, with fencing to be installed on Friday, April 26, 2024 and actual construction to begin on Monday, April 29, 2024.
Picture story telling starts here. Newest photo first, oldest photos at the end (here).